Question No. 6. For total reaction time of 2.5 seconds, coefficient of friction 0.35, design speed 80 km/h, what is the stopping sight distance on a highway ? A. 127 m B. 132 m C. 76 m D. 56 m Show Answer Answer Answer: Option A Question No. 7. What is the use of a […]
Category: Upsc Civil MCQ
UPSC Civil Service Exam Questions – Section 1
Question No. 1. The following steps are involved in laying a sewer in a trench : 1. Transferring the center line of the sewer to the bottom trench. 2. Setting sight rails over the trench. 3. Driving pegs to the level of the invert line of the sewer. 4. Placing the sewer of these steps […]