Civil Engg Calculator

12 MM CEMENT PLASTER CALCULATOR

12 MM CEMENT PLASTER CALCULATOR

Click to expand

Plaster Area Calculation


Material Calculation

Volume of Mortar = Area of Plaster x Thickness of Plaster

Note – Add 20% to fill up Joint and Cover the Surface

Surface)  = 1.44

(A) For 12mm Cement Plaster (1:6)

Note – Increases by 25% of the Total Dry Volume
         ————(For 100 m2 Plaster Area)

For 1 m2 Plaster Area = 1.80/100 = 0.018 m2 Dry Volume of Mortar Needed

Surface)  = 0.018

Step 1: Amount of Cement Required

 

   

 

   

Cement Required = 0.00257 m3

 

Step 2: Quantity of Coarse Sand Required

   

 

   

Coarse Sand Required = 0.01542 m3

Note: By considering dry density of sand = 1550 kg/m3


(B) For 12mm Cement Plaster (1:5)

For Cement Mortar (1:5)

Note – Increases by 28.4% of the Total Dry Volume Cement Mortar (1:5)

According to BCD Analysis Rates 2114 Cement Mortar (1:5)

Corse Sand = 1.07 m3

Cement Required = 0.214 m3 (1.07/5)

Then Total Volume = 1.07+0.214 = 1.284 m3

         ————(For 100 m2 Plaster Area)

For 1 m2 Plaster Area = 1.8489/100 = 0.018489 m2 Dry Volume of Mortar Needed

Step 1: Amount of Cement Required

 

   

 

   

Cement Required = 0.00308 m3

 

Step 2: Quantity of Coarse Sand Required

   

 

   

Coarse Sand Required = 0.01541 m3

Note: By considering dry density of sand = 1550 kg/m3


(C) For 12mm Cement Plaster (1:4)

For Cement Mortar (1:4)

Note – Increases by 34% of the Total Dry Volume Cement Mortar (1:4)

According to BCD Analysis Rates 2114 Cement Mortar (1:4)

Corse Sand = 1.07 m3

Cement Required = 0.2675 m3 (1.07/4)

Then Total Volume = 1.07+0.2675 = 1.3375 m3

         ————(For 100 m2 Plaster Area)

For 1 m2 Plaster Area = 1.9296/100 = 0.019296 m2 Dry Volume of Mortar Needed

Step 1: Amount of Cement Required

 

   

 

   

Cement Required = 0.003859 m3

 

Step 2: Quantity of Coarse Sand Required

   

 

   

Coarse Sand Required = 0.01541 m3

Note: By considering dry density of sand = 1550 kg/m3


(D) For 12mm Cement Plaster (1:3)

For Cement Mortar (1:3)

Note – Increases by 42.7% of the Total Dry Volume Cement Mortar (1:4)

According to BCD Analysis Rates 2114 Cement Mortar (1:3)

Corse Sand = 1.07 m3

Cement Required = 0.357 m3 (1.07/3)

Then Total Volume = 1.07+0.357 = 1.427 m3

         ————(For 100 m2 Plaster Area)

For 1 m2 Plaster Area = 2.055/100 = 0.02055 m2 Dry Volume of Mortar Needed

Step 1: Amount of Cement Required

 

   

 

   

Cement Required = 0.00514 m3

 

Step 2: Quantity of Coarse Sand Required

   

 

   

Coarse Sand Required = 0.01541 m3

Note: By considering dry density of sand = 1550 kg/m3


(E) For 12mm Cement Plaster (1:3) with a Floating Coat of Neat Cement

Cement Required = 0.00514 m3

Coarse Sand Required = 0.01541 m3

For Floating Coat of Neat Cement  2kg/mCement Will Be Added

Step 1: Amount of Cement Required

Cement = 0.00514+0.0014 = 0.00654 m3

Step 2: Quantity of Coarse Sand Required

Same As Above

Coarse Sand Required = 0.01541 m3


(F) For 12mm Cement Plaster (1:4) with a Floating Coat of Neat Cement

Cement Required = 0.003859 m3

Coarse Sand Required = 0.01541 m3

For Floating Coat of Neat Cement  2kg/mCement Will Be Added

Step 1: Amount of Cement Required

Cement = 0.003859+0.0014 = 0.00526 m3

Step 2: Quantity of Coarse Sand Required

Same As Above

Coarse Sand Required = 0.01541 m3

Civil

Recent Posts

Delhi Schedule of Rate 2023 Civil PDF Free Download

Delhi Schedule of Rate (DSR) 2023 Civil भारत  में भवनों का प्राक्कलन  गठन करने हेतु…

5 months ago

Minimum Requirement for Fire Fighting Installations of a Residential and Non Residential Buildings

Minimum Requirement for Fire Fighting Installations प्रत्येक भवन को इस प्रकार डिज़ाइन, निर्मित, सुसज्जित, रखरखाव…

5 months ago

Jharkhand Building Schedule of Rates 2015 PDF Free Download

Jharkhand Building Schedule of Rates झारखण्ड  राज्य में भवनों का प्राक्कलन  गठन करने हेतु हमें…

6 months ago

Jharkhand Building Schedule of Rates 2014 PDF Free Download

Jharkhand Building Schedule of Rates झारखण्ड  राज्य में भवनों का प्राक्कलन  गठन करने हेतु हमें…

6 months ago

बिहार ठीकेदारी नियमावली 2007 – पथ निर्माण विभाग

बिहार ठीकेदारी नियमावली 2007 - पथ निर्माण विभाग Bihar Thikedari Nayamawali 2007 Overview Name of…

6 months ago

Tripura PWD Road and Bridge Schedule of Rates 2023 PDF Free Download

Tripura  PWD Road and Bridge Schedule of Rates 2023 Tripura Schedule of Rates being published…

11 months ago