12 MM CEMENT |
Volume of Mortar = Area of Plaster x Thickness of Plaster
Note – Add 20% to fill up Joint and Cover the Surface |
Surface) = 1.44 |
(A) For 12mm Cement Plaster (1:6) |
Note – Increases by 25% of the Total Dry Volume
————(For 100 m2 Plaster Area)
For 1 m2 Plaster Area = 1.80/100 = 0.018 m2 Dry Volume of Mortar Needed
Surface) = 0.018 |
Cement Required = 0.00257 m3
Coarse Sand Required = 0.01542 m3
Note: By considering dry density of sand = 1550 kg/m3
(B) For 12mm Cement Plaster (1:5) |
For Cement Mortar (1:5)
Note – Increases by 28.4% of the Total Dry Volume Cement Mortar (1:5) According to BCD Analysis Rates 2114 Cement Mortar (1:5) Corse Sand = 1.07 m3 Cement Required = 0.214 m3 (1.07/5) Then Total Volume = 1.07+0.214 = 1.284 m3 |
————(For 100 m2 Plaster Area)
For 1 m2 Plaster Area = 1.8489/100 = 0.018489 m2 Dry Volume of Mortar Needed
Cement Required = 0.00308 m3
Coarse Sand Required = 0.01541 m3
Note: By considering dry density of sand = 1550 kg/m3
(C) For 12mm Cement Plaster (1:4) |
For Cement Mortar (1:4)
Note – Increases by 34% of the Total Dry Volume Cement Mortar (1:4) According to BCD Analysis Rates 2114 Cement Mortar (1:4) Corse Sand = 1.07 m3 Cement Required = 0.2675 m3 (1.07/4) Then Total Volume = 1.07+0.2675 = 1.3375 m3 |
————(For 100 m2 Plaster Area)
For 1 m2 Plaster Area = 1.9296/100 = 0.019296 m2 Dry Volume of Mortar Needed
Cement Required = 0.003859 m3
Coarse Sand Required = 0.01541 m3
Note: By considering dry density of sand = 1550 kg/m3
(D) For 12mm Cement Plaster (1:3) |
For Cement Mortar (1:3)
Note – Increases by 42.7% of the Total Dry Volume Cement Mortar (1:4) According to BCD Analysis Rates 2114 Cement Mortar (1:3) Corse Sand = 1.07 m3 Cement Required = 0.357 m3 (1.07/3) Then Total Volume = 1.07+0.357 = 1.427 m3 |
————(For 100 m2 Plaster Area)
For 1 m2 Plaster Area = 2.055/100 = 0.02055 m2 Dry Volume of Mortar Needed
Cement Required = 0.00514 m3
Coarse Sand Required = 0.01541 m3
Note: By considering dry density of sand = 1550 kg/m3
(E) For 12mm Cement Plaster (1:3) with a Floating Coat of Neat Cement |
Cement Required = 0.00514 m3
Coarse Sand Required = 0.01541 m3
For Floating Coat of Neat Cement 2kg/m2 Cement Will Be Added
Cement = 0.00514+0.0014 = 0.00654 m3
Same As Above
Coarse Sand Required = 0.01541 m3
(F) For 12mm Cement Plaster (1:4) with a Floating Coat of Neat Cement |
Cement Required = 0.003859 m3
Coarse Sand Required = 0.01541 m3
For Floating Coat of Neat Cement 2kg/m2 Cement Will Be Added
Cement = 0.003859+0.0014 = 0.00526 m3
Same As Above
Coarse Sand Required = 0.01541 m3
Delhi Schedule of Rate (DSR) 2023 Civil भारत में भवनों का प्राक्कलन गठन करने हेतु…
Minimum Requirement for Fire Fighting Installations प्रत्येक भवन को इस प्रकार डिज़ाइन, निर्मित, सुसज्जित, रखरखाव…
Jharkhand Building Schedule of Rates झारखण्ड राज्य में भवनों का प्राक्कलन गठन करने हेतु हमें…
Jharkhand Building Schedule of Rates झारखण्ड राज्य में भवनों का प्राक्कलन गठन करने हेतु हमें…
बिहार ठीकेदारी नियमावली 2007 - पथ निर्माण विभाग Bihar Thikedari Nayamawali 2007 Overview Name of…
Tripura PWD Road and Bridge Schedule of Rates 2023 Tripura Schedule of Rates being published…