Civil Engg Calculator

20 MM CEMENT PLASTER CALCULATOR

20 MM CEMENT PLASTER CALCULATOR

Click to expand

Plaster Area Calculation


Material Calculation

Volume of Mortar = Area of Plaster x Thickness of Plaster

Note – Add 12% to fill up Joint and Cover the Surface

Surface)  = 2.24

(A) For 20mm Cement Plaster (1:6)

Note – Increases by 25% of the Total Dry Volume
         ————(For 100 m2 Plaster Area)

For 1 m2 Plaster Area = 2.80/100 = 0.028 m3 Dry Volume of Mortar Needed

Surface)  = 0.0215

Step 1: Amount of Cement Required

 

   

 

   

Cement Required = 0.004 m3

 

Step 2: Quantity of Coarse Sand Required

   

 

   

Coarse Sand Required = 0.024 m3

Note: By considering dry density of sand = 1550 kg/m3


(B) For 20mm Cement Plaster (1:5)

For Cement Mortar (1:5)

Note – Increases by 28.4% of the Total Dry Volume Cement Mortar (1:5)

According to BCD Analysis Rates 2114 Cement Mortar (1:5)

Corse Sand = 1.07 m3

Cement Required = 0.214 m3 (1.07/5)

Then Total Volume = 1.07+0.214 = 1.284 m3

         ————(For 100 m2 Plaster Area)

For 1 m2 Plaster Area = 2.876/100 = 0.02876 m3 Dry Volume of Mortar Needed

Step 1: Amount of Cement Required

 

   

 

   

Cement Required = 0.004794 m3

 

Step 2: Quantity of Coarse Sand Required

   

 

   

Coarse Sand Required = 0.0024 m3

Note: By considering dry density of sand = 1550 kg/m3


(C) For 20mm Cement Plaster (1:4)

For Cement Mortar (1:4)

Note – Increases by 34% of the Total Dry Volume Cement Mortar (1:4)

According to BCD Analysis Rates 2113 Cement Mortar (1:4)

Corse Sand = 1.07 m3

Cement Required = 0.2675 m3 (1.07/4)

Then Total Volume = 1.07+0.2675 = 1.3375 m3

         ————(For 100 m2 Plaster Area)

For 1 m2 Plaster Area = 3.0016/100 = 0.03 m3 Dry Volume of Mortar Needed

Step 1: Amount of Cement Required

 

   

 

   

Cement Required = 0.006 m3

 

Step 2: Quantity of Coarse Sand Required

   

 

   

Coarse Sand Required = 0.024 m3

Note: By considering dry density of sand = 1550 kg/m3


(D) For 20mm Cement Plaster (1:3)

For Cement Mortar (1:3)

Note – Increases by 42.7% of the Total Dry Volume Cement Mortar (1:4)

According to BCD Analysis Rates 2114 Cement Mortar (1:3)

Corse Sand = 1.07 m3

Cement Required = 0.357 m3 (1.07/3)

Then Total Volume = 1.07+0.357 = 1.427 m3

         ————(For 100 m2 Plaster Area)

For 1 m2 Plaster Area = 3.196/100 = 0.03196 m2 Dry Volume of Mortar Needed

Step 1: Amount of Cement Required

 

   

 

   

Cement Required = 0.00799 m3

 

Step 2: Quantity of Coarse Sand Required

   

 

   

Coarse Sand Required = 0.024 m3

Note: By considering dry density of sand = 1550 kg/m3


 

 

Civil

Share
Published by
Civil

Recent Posts

Tripura PWD Road and Bridge Schedule of Rates 2023 PDF Free Download

Tripura  PWD Road and Bridge Schedule of Rates 2023 Tripura Schedule of Rates being published…

5 months ago

Tripura PWD Building Schedule of Rates 2023 PDF Free Download

Tripura PWD Building Schedule of Rates 2023 Tripura Schedule of Rates being published by  Public…

5 months ago

MILITARY ENGINEER SERVICES SCHEDULE OF RATES 2020 PDF Free Download

MILITARY ENGINEER SERVICES SCHEDULE OF RATES 2020 MES Standard Schedule of Rates Part II covering…

5 months ago

बिहार ठीकेदारी नियमावली 2007 – पथ निर्माण विभाग

बिहार ठीकेदारी नियमावली 2007 - पथ निर्माण विभाग Bihar Thikedari Nayamawali 2007 Overview Name of…

5 months ago

BCD Electric SOR 2023 – Download Electric SOR Bihar 2023

BCD Electric SOR 2023 बिहार राज्य में भवनों का प्राक्कलन  गठन करने हेतु हमें कुछ…

7 months ago

15 MM CEMENT PLASTER CALCULATOR

15 MM CEMENT PLASTER CALCULATOR Plaster Area Calculation PlasterArea = Length × Width Plaster Area…

9 months ago