Question No.6.

The principle of “working from whole to part” is used in surveying because

[Utarakhand JE 2016]

Answer

Answer:Option C


Question No. 7.

The type of surveying in which the curvature of the earth is taken into account is called….

[SSC JE 2 MARCH 2017 Morning Shift ]

Answer

Answer:Option A


Question No. 8.

The measurement of longitudinal section survey is done on which basis?

[NPCC JE 21 Jan 2017]

Answer

Answer:Option A


Question No. 9.

Permissible limits of error in chaining for measurement on rough or hilly ground is ……

[SSC JE 1 MARCH 2017 Evening Shift]

Answer

Answer:Option D


Question No. 10.

The point of the celestial sphere vertically below the observa’s position is called:

[RJC Exam, 21-08-2016]

Answer

Answer:Option D


Civil

Recent Posts

Latest Bihar Schedule of Rates | PWD, WRD, BCD, RCD, CIVIL , Electrical

Latest Bihar Schedule of Rates   What is a Schedule of Rates (SOR)? A Schedule…

1 month ago

WRD SOR 2025 Bihar Pdf free Download

Water Resources Department Schedule of Rates 2025 Pdf (Effective From 13.02.2025) Water Resources Department is…

1 month ago

WRD SOR 2023 Bihar Pdf free Download

Water Resources Department Schedule of Rates 2023 Pdf (Effective From 03.11.2023) Water Resources Department is…

2 months ago

Delhi Schedule of Rate 2023 Civil PDF Free Download

Delhi Schedule of Rate (DSR) 2023 Civil भारत  में भवनों का प्राक्कलन  गठन करने हेतु…

12 months ago

Minimum Requirement for Fire Fighting Installations of a Residential and Non Residential Buildings

Minimum Requirement for Fire Fighting Installations प्रत्येक भवन को इस प्रकार डिज़ाइन, निर्मित, सुसज्जित, रखरखाव…

12 months ago

Jharkhand Building Schedule of Rates 2015 PDF Free Download

Jharkhand Building Schedule of Rates झारखण्ड  राज्य में भवनों का प्राक्कलन  गठन करने हेतु हमें…

12 months ago