20 MM CEMENT |
Volume of Mortar = Area of Plaster x Thickness of Plaster
Note – Add 12% to fill up Joint and Cover the Surface |
Surface) = 2.24 |
(A) For 20mm Cement Plaster (1:6) |
Note – Increases by 25% of the Total Dry Volume
————(For 100 m2 Plaster Area)
For 1 m2 Plaster Area = 2.80/100 = 0.028 m3 Dry Volume of Mortar Needed
Surface) = 0.0215 |
Cement Required = 0.004 m3
Coarse Sand Required = 0.024 m3
Note: By considering dry density of sand = 1550 kg/m3
(B) For 20mm Cement Plaster (1:5) |
For Cement Mortar (1:5)
Note – Increases by 28.4% of the Total Dry Volume Cement Mortar (1:5) According to BCD Analysis Rates 2114 Cement Mortar (1:5) Corse Sand = 1.07 m3 Cement Required = 0.214 m3 (1.07/5) Then Total Volume = 1.07+0.214 = 1.284 m3 |
————(For 100 m2 Plaster Area)
For 1 m2 Plaster Area = 2.876/100 = 0.02876 m3 Dry Volume of Mortar Needed
Cement Required = 0.004794 m3
Coarse Sand Required = 0.0024 m3
Note: By considering dry density of sand = 1550 kg/m3
(C) For 20mm Cement Plaster (1:4) |
For Cement Mortar (1:4)
Note – Increases by 34% of the Total Dry Volume Cement Mortar (1:4) According to BCD Analysis Rates 2113 Cement Mortar (1:4) Corse Sand = 1.07 m3 Cement Required = 0.2675 m3 (1.07/4) Then Total Volume = 1.07+0.2675 = 1.3375 m3 |
————(For 100 m2 Plaster Area)
For 1 m2 Plaster Area = 3.0016/100 = 0.03 m3 Dry Volume of Mortar Needed
Cement Required = 0.006 m3
Coarse Sand Required = 0.024 m3
Note: By considering dry density of sand = 1550 kg/m3
(D) For 20mm Cement Plaster (1:3) |
For Cement Mortar (1:3)
Note – Increases by 42.7% of the Total Dry Volume Cement Mortar (1:4) According to BCD Analysis Rates 2114 Cement Mortar (1:3) Corse Sand = 1.07 m3 Cement Required = 0.357 m3 (1.07/3) Then Total Volume = 1.07+0.357 = 1.427 m3 |
————(For 100 m2 Plaster Area)
For 1 m2 Plaster Area = 3.196/100 = 0.03196 m2 Dry Volume of Mortar Needed
Cement Required = 0.00799 m3
Coarse Sand Required = 0.024 m3
Note: By considering dry density of sand = 1550 kg/m3
Delhi Schedule of Rate (DSR) 2023 Civil भारत में भवनों का प्राक्कलन गठन करने हेतु…
Minimum Requirement for Fire Fighting Installations प्रत्येक भवन को इस प्रकार डिज़ाइन, निर्मित, सुसज्जित, रखरखाव…
Jharkhand Building Schedule of Rates झारखण्ड राज्य में भवनों का प्राक्कलन गठन करने हेतु हमें…
Jharkhand Building Schedule of Rates झारखण्ड राज्य में भवनों का प्राक्कलन गठन करने हेतु हमें…
बिहार ठीकेदारी नियमावली 2007 - पथ निर्माण विभाग Bihar Thikedari Nayamawali 2007 Overview Name of…
Tripura PWD Road and Bridge Schedule of Rates 2023 Tripura Schedule of Rates being published…