20 MM CEMENT PLASTER CALCULATOR

Click to expand

Plaster Area Calculation


Material Calculation

Volume of Mortar = Area of Plaster x Thickness of Plaster

Note – Add 12% to fill up Joint and Cover the Surface

Surface)  = 2.24

(A) For 20mm Cement Plaster (1:6)

Note – Increases by 25% of the Total Dry Volume
         ————(For 100 m2 Plaster Area)

For 1 m2 Plaster Area = 2.80/100 = 0.028 m3 Dry Volume of Mortar Needed

Surface)  = 0.0215

Step 1: Amount of Cement Required

 

   

 

   

Cement Required = 0.004 m3

 

Step 2: Quantity of Coarse Sand Required

   

 

   

Coarse Sand Required = 0.024 m3

Note: By considering dry density of sand = 1550 kg/m3


(B) For 20mm Cement Plaster (1:5)

For Cement Mortar (1:5)

Note – Increases by 28.4% of the Total Dry Volume Cement Mortar (1:5)

According to BCD Analysis Rates 2114 Cement Mortar (1:5)

Corse Sand = 1.07 m3

Cement Required = 0.214 m3 (1.07/5)

Then Total Volume = 1.07+0.214 = 1.284 m3

         ————(For 100 m2 Plaster Area)

For 1 m2 Plaster Area = 2.876/100 = 0.02876 m3 Dry Volume of Mortar Needed

Step 1: Amount of Cement Required

 

   

 

   

Cement Required = 0.004794 m3

 

Step 2: Quantity of Coarse Sand Required

   

 

   

Coarse Sand Required = 0.0024 m3

Note: By considering dry density of sand = 1550 kg/m3


(C) For 20mm Cement Plaster (1:4)

For Cement Mortar (1:4)

Note – Increases by 34% of the Total Dry Volume Cement Mortar (1:4)

According to BCD Analysis Rates 2113 Cement Mortar (1:4)

Corse Sand = 1.07 m3

Cement Required = 0.2675 m3 (1.07/4)

Then Total Volume = 1.07+0.2675 = 1.3375 m3

         ————(For 100 m2 Plaster Area)

For 1 m2 Plaster Area = 3.0016/100 = 0.03 m3 Dry Volume of Mortar Needed

Step 1: Amount of Cement Required

 

   

 

   

Cement Required = 0.006 m3

 

Step 2: Quantity of Coarse Sand Required

   

 

   

Coarse Sand Required = 0.024 m3

Note: By considering dry density of sand = 1550 kg/m3


(D) For 20mm Cement Plaster (1:3)

For Cement Mortar (1:3)

Note – Increases by 42.7% of the Total Dry Volume Cement Mortar (1:4)

According to BCD Analysis Rates 2114 Cement Mortar (1:3)

Corse Sand = 1.07 m3

Cement Required = 0.357 m3 (1.07/3)

Then Total Volume = 1.07+0.357 = 1.427 m3

         ————(For 100 m2 Plaster Area)

For 1 m2 Plaster Area = 3.196/100 = 0.03196 m2 Dry Volume of Mortar Needed

Step 1: Amount of Cement Required

 

   

 

   

Cement Required = 0.00799 m3

 

Step 2: Quantity of Coarse Sand Required

   

 

   

Coarse Sand Required = 0.024 m3

Note: By considering dry density of sand = 1550 kg/m3


 

 

Civil

Share
Published by
Civil

Recent Posts

Schedule of Rates (SOR) क्या है? | A Complete Beginner’s Guide

अगर आप construction industry से जुड़े हैं या फिर किसी government project के बारे में…

6 hours ago

Telangana Schedule of Rates 2025-26 PDF Free Download

Telangana SOR क्या है और क्यों जरूरी है? Schedule of Rates यानी SOR एक official…

1 day ago

BCD SOR in Excel | Bihar Schedule of Rates Excel Format

BCD SOR in Excel BCD SOR क्या है? BCD SOR (Bihar Schedule of Rates) एक…

6 days ago

Types of Vibrators Used in Construction: A Complete Guide

Types of Vibrators Used in Construction: A Complete Guide कंक्रीट की quality और durability सुनिश्चित…

2 weeks ago

Bihar BCD SOR 2025 | UPDATED SCHEDULE OF RATES FREE DOWNLOAD

BCD SOR 2025 क्या है? UPDATED SOR BY BCD भारतीय निर्माण कार्यों में SOR (Schedule…

2 weeks ago

25+ Common Mistakes in Construction जो आपको लाखों का नुकसान दे सकती हैं

25+ Common Mistakes in Construction पिछले महीने मेरे पड़ोसी का घर बनकर तैयार हुआ। बाहर…

3 weeks ago

This website uses cookies.